Over the last several months and working throughout the summer. Our team has collectively accomplished a great deal. Engineering/permit drawings were completed in August. We are finalizing our permits for construction now with the City of Luperon. The first two of nine permits are all from the city of Luperon. These are required to move forward. The mayor and the city council have been presented our development and agree on the permitting our project. The balance of the permits are required but not until just before commencing the various aspects of infrastructure construction, such as electrical, water and sewer etc.
We are now in the wet season and we will not execute the infrastructures construction until January of 2018, otherwise we risk the heavy road grading and excavation eroding if there are heavy rains, like there was last year.
Look for more frequent updates on the general development between now and the end of this year.